Demolition of the old Kurfürstenbad

Following a public tender, the city of Bonn commissioned Wahl Abbruch GmbH with the services for the above-ground demolition of the Kurfürstenbad. This contract included the following services: Gutting, pollutant clean-up, preparatory work to remove and secure the Paul Magar mosaic and mechanical dismantling.

In the course of execution, there were growing differences between the contractor, Wahl, and the City of Bonn as the client. Ultimately, these differences led to an extraordinary termination on July 22, 2024, and alternatively to an ordinary termination. As these are pending legal proceedings, no further details can be provided at present.

The City of Bonn intends to have the outstanding dismantling work carried out by a total contractor - with the aim of minimizing a possible extension of the construction period.